The Boston Parks Department will present a revised proposal for the reconstruction of Library Park next Tuesday, April 3 at 5:30 PM at City Hall's Fifth Floor Piemonte Room. At the previous presentation in January to the South End Landmark District Commission, the project director, Lauren Bryant, was asked to come back with an amended proposal to include the commissioners' concerns about protection of the park's oak trees root systems, easy flow of foot traffic unimpeded by park furniture and an upgraded, more interesting hardscape that would include some details of typical South End materials like brick, slate or bluestone. The redesign of the redesign was different enough to require a second public hearing about Library Park's future, which was held at the South End library on Wednesday, March 22.
The March 22nd public hearing solicited a number of comments, including a request to create more intimate spaces through seating and paving areas. There was a question about what to do with the granite blocks that are a play opportunity for kids, but uncomfortable to sit on; a request to inset tables with game boards; and a concern that the seating feels restrictive given that it lines both sides of the plaza. The single chairs of the current park appear to be in good shape and will be re-used and matched in style with additional curved benches, cafe tables and chairs. The oak trees will be pruned.
A large part of the work will be devoted to improving the park's infrastructure, including the clean-up of the site, underneath which there is expected to be a great deal of remnants from previous housing, including oil tanks and a lot of bricks. The soil will be improved and re-graded to enhance future landscaping. Another important aspect of the reconstruction will be groundwater management and water filtration to benefit root systems of trees, shrubs and plantings.
At the first public hearing in November last year, Parks Department's Bryant and Brandon Kunkel, landscape architect with the Weston & Sampson design and engineering firm, presented attendees with three proposals. The one below was favored by the audience and was presented to Landmarks in January, but has been altered to comply with Landmarks's comments.
After deducting the cost of design services, the remaining budget for the reconfiguration is $115,000, a small amount, which will be augmented with private fundraising efforts by the Friends of the South End Library until a more comprehensive renovation of library and park will take place in the next few years. Further information about the current project can be obtained at the Parks Department website, linked here.